Stakeholders’ issues as a source of project delays: a meta-analysis between building and road projects
DOI:
https://doi.org/10.7764/RDLC.22.1.51Keywords:
delay causes; delay factors; road projects; building projects; meta-analysis.Abstract
Delay is one of the most common and complex issues that adversely affect the performance of construction pro-jects. Although much research exists on project delay, only some studies have systematically summarized and compared the causes of delay by the project type. In addition, few studies have quantitatively combined the variability across studies and related them to the responsibilities of project stakeholders. This study conducted a meta-analysis to provide quantitative and reliable evidence on delay causes combining previous research. This study categorized the top ten causes of delay published in primary research studies, calculated the average aggregate relative important index (RII) of these causes, quantitatively summarized their impact on building and road projects using meta-analysis techniques, and linked them to stakeholder responsibility. Based on an initial 160 top ten-delay causes reported, the study aggregated them into sixteen factors and seven management areas. This research found a different prioritization of delays by project type. Overall, while "site management & technical processes" was the most critical delay factor for building projects, "external issue" was for road projects. The comparison by region shows that "skills, knowledge & experience" was the most critical factor for African studies, but "late delivery and material-equipment issues" was for Asian studies. These factors were related to project stakeholders for defining mitigation actions that led to better project performance. Finally, this study provides a first taxonomy of delays, where the previous causes reported in the literature were clustered into factors and management areas.
Downloads
References
Abdellatif, H., & Alshibani, A. (2019). Major factors causing delay in the delivery of manufacturing and building projects in Saudi Arabia. Buildings, 9(4), 93. https://doi.org/10.3390/buildings9040093
Adeyemi, A., & Masalila, K. (2016). Delay Factors and Time-Cost Performance of Construction Projects in Gaborone City Council, Botswana. Journal for the Advancement of Performance Information and Value, 8(1), 4–1. https://doi.org/10.37265/japiv.v8i1.46
Aforla, B., Woode, A., & Amoah, D. K. (2016). Causes of delays in highway construction projects in Ghana. Civil and Environmental Research, 8(11), 69–76.
Ahiwako, O., Oloke, D., Suresh, S., & Khatib, J. (2015). Implementing The Last Planner System in a Road Construction Project in Nigeria. Built Environ-ment Journal, 12(2), 32–49.
Aibinu, A. A., & Odeyinka, H. A. (2006). Construction delays and their causative factors in Nigeria. Journal of Construction Engineering and Manage-ment, 132(7), 667–677. https://doi.org/10.1061/(asce)0733-9364(2006)132:7(667)
Akogbe, R. K. T. M., Feng, X., & Zhou, J. (2013). Importance and ranking evaluation of delay factors for development construction projects in Benin. KSCE Journal of Civil Engineering, 17(6), 1213–1222. https://doi.org/10.1007/s12205-013-0446-2
Al-Hazim, N., Salem, Z. A., & Ahmad, H. (2017). Delay and cost overrun in infrastructure projects in Jordan. Procedia Engineering, 182, 18–24. https://doi.org/10.1016/j.proeng.2017.03.105
Alaghbari, W., Kadir, M. R. A., Salim, A., & Ernawati. (2007). The significant factors causing delay of building construction projects in Malaysia. Engineer-ing, Construction and Architectural Management, 14(2), 192–206. https://doi.org/10.1108/09699980710731308
AlGheth, A., & Sayuti, I. (2019). An Investigation of Causes of Delay Affecting the United Arab Emirates Construction Industry. International Confer-ence on Civil Engineering, 403–413.
Alinaitwe, H. M., Mwakali, J. A., & Hansson, B. (2007). Factors affecting the productivity of building craftsmen - studies of Uganda. Journal of Civil Engineering and Management, 13(3), 169–176. https://doi.org/10.1080/13923730.2007.9636434
Amoatey, C., Ameyaw, A., Adaku, E., & Famiyeh, S. (2015). Analysing delay causes and effects in Ghanaian state housing construction projects. Interna-tional Journal of Managing Projects in Business, 8(1), 198–214. https://doi.org/10.1108/IJMPB-04-2014-0035
Amoatey, C., & Okanta, A. (2017). Exploring critical road project delay factors in Ghana. Journal of Facilities Management, 15(2), 110–127. Retrieved from https://doi.org/10.1108/JFM-09-2016-0036
Asiedu, R., & Alfen, H. (2016). Understanding the underlying reasons behind time overruns of government building projects in Ghana. KSCE Journal of Civil Engineering, 20(6), 2103–2111. https://doi.org/10.1007/s12205-015-0544-4
Aziz, R. F., & Abdel-Hakam, A. A. (2016). Exploring delay causes of road construction projects in Egypt. Alexandria Engineering Journal, 55(2), 1515–1539. https://doi.org/10.1016/j.aej.2016.03.006
Ballesteros-pérez, P., Sanz-ablanedo, E., Mora-melià, D., González-cruz, M. C., Fuentes-Bargues, J., & Pellicer, E. (2019). Earned schedule min-max: Two new EVM metrics for monitoring and controlling projects. Automation in Construction, 103(November 2018), 279–290. https://doi.org/10.1016/j.autcon.2019.03.016
Barati, K., & Shen, X. (2016). Operational level emissions modelling of on-road construction equipment through field data analysis. Automation in Con-struction, 72, 338–346. https://doi.org/10.1016/j.autcon.2016.08.010
Boreinstein, M., Rothstein, H., Hedges, L. V., & Higgins, J. P. T. (2009). Introduction to meta-analysis. In Copyright © 2009 John Wiley & Sons, Ltd.
Card, N. A. (2016). Applied meta-analysis for social science research. In New York: The Guilford Press.
Chang, A. (2002). Reasons for cost and schedule increase for engineering design projects. Journal of Management in Engineering, 18(1), 29–36. https://doi.org/10.1061/(ASCE)0742-597X(2002)18:1(29)
Daniel, E. I. (2017). Exploratory study into the use of Last Planner® System and collaborative planning for construction process improvement. Notting-ham Trent University.
Durdyev, S., Omarov, M., & Ismail, S. (2017). Causes of delay in residential construction projects in Cambodia. Cogent Engineering, 4(1), 1–12. https://doi.org/10.1080/23311916.2017.1291117
Eldin, N. (2002). Road construction: Materials and methods. Journal of Environmental Engineering, 128(5), 423–430. https://doi.org/10.1061/(ASCE)0733-9372(2002)128:5(423)
Ellis, R. D. (2003). The root causes of delays in highway construction. Presentation at the 82nd Annual Meeting of the Transportation Research Board, 1–16. Washington, USA.
Emam, H., Farrell, P., & Abdelaal, M. (2015). Causes of delay on infrastructure projects in Qatar. Proceedings of 31st Annual ARCOM Conference, (Sep-tember), 773–782. Linconln, UK: Association of Researchers in Construction Management.
Eriksson, P. E. (2015). Partnering in engineering projects: four dimensions of supply chain integration. Journal of Purchasing and Supply Management, 21(1), 38–50. https://doi.org/10.1016/j.pursup.2014.08.003
Famiyeh, S., Amoatey, C. T., & Adaku, E. (2017). Major causes of construction time and cost overruns: a case of selected educational sector projects in Ghana. Journal of Engineering, Design and Technology, 15(2), 181–198. https://doi.org/10.1108/JEDT-11-2015-0075
Holt, G. D. (2013). Asking questions, analysing answers: Relative importance revisited. Construction Innovation, 14(1), 2–16. https://doi.org/10.1108/CI-06-2012-0035
Honrao, Y., & Desai, D. (2015). Study of Delay in Execution of Infrastructure Projects –. International Journal of Scientific and Research Publications, 5(6), 1–8.
Hussain, S., Zhu, F., Ali, Z., Aslam, H. D., & Hussain, A. (2018). Critical delaying factors: Public sector building projects in Gilgit-Baltistan, Pakistan. Build-ings, 8(1), 1–16. https://doi.org/10.3390/buildings8010006
Kaliba, C., Muya, M., & Mumba, K. (2009). Cost escalation and schedule delays in road construction projects in Zambia. International Journal of Project Management, 27(5), 522–531. https://doi.org/10.1016/j.ijproman.2008.07.003
Khair, K., Mohamed, Z., Mohammad, R., Farouk, H., & Ahmed, M. (2017). A management framework to reduce delays in road construction projects in Sudan. Arabian Journal for Science and Engineering, 43(4), 1925–1940. https://doi.org/10.1007/s13369-017-2806-6
Larsen, J. K., Shen, G. Q., Lindhard, S. M., & Brunoe, T. D. (2016). Factors Affecting Schedule Delay, Cost Overrun, and Quality Level in Public Construc-tion Projects. Journal of Management in Engineering. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000391
Love, P. E. D., Smith, J., Simpson, I., Regan, M., & Olatunji, O. (2015). Understanding the landscape of overruns in transport infrastructure projects. Envi-ronment and Planning B: Urban Analytics and City Science, 42(3), 490–509. https://doi.org/10.1068/b130102p
Mahamid, I. (2017). Analysis of schedule deviations in road construction projects and the effects of project physical characteristics. Journal of Financial Management of Property and Construction, 22(2), 192–210. https://doi.org/10.1108/jfmpc.2008.37613aaa.002
Mahamid, I., Bruland, A., & Dmaidi, N. (2012). Causes of delay in road construction projects. Journal of Management in Engineering, 28(3), 300–310. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000096
Mate, R., & Hinge, G. (2015). Delay mitigation in the construction industry. International Journal of Engineering Research & Technology, 4(6), 172–176.
Meeampol, S., & Ogunlan, S. O. (2006). Factors affecting cost and time performance on highway construction projects: Evidence from Thailand. Journal of Financial Management of Property and Construction. https://doi.org/10.1108/13664380680001076
Memari, A. M., Huelman, P. H., Iulo, L. D., Laquatra, J., Martin, C., McCoy, A., … Williamson, T. (2014). Residential building construction: State-of-the-art review. Journal of Architectural Engineering, 20(4), 1–38. https://doi.org/10.1061/(ASCE)AE.1943-5568.0000157
Mok, K. Y., Shen, G. Q., & Yang, J. (2015). Stakeholder management studies in mega construction projects: A review and future directions. International Journal of Project Management. https://doi.org/10.1016/j.ijproman.2014.08.007
Nasir, A. R., Gabriel, H., & Choudhry, R. (2015). Cost and time overruns in highway projects of Pakistan. Sixth International Conference on Construction in the 21st Century, (May), 69–76. Kuala Lumpur, Malaysia.
Nations United. (2020). UNECE Statistical Database. Retrieved from United Nations Economic Commission for Europe. Retrieved July 20, 2020, from https://w3.unece.org/PXWeb/en/CountryRanking?IndicatorCode=8.
Neyeloff, J. L., Fuchs, S. C., & Moreira, L. B. (2012). Meta-analyses and Forest plots using a microsoft excel spreadsheet: Step-by-step guide focusing on descriptive data analysis. BMC Research Notes, 5(Mix). https://doi.org/10.1186/1756-0500-5-52
Othuman Mydin, M. A., Sani, N. M., Taib, M., & Mohd Alias, N. (2014). Imperative causes of delays in construction projects from developers’ outlook. MATEC Web of Conferences, 10, 1–6. https://doi.org/10.1051/matecconf/20141006005
Oyegoke, A. S., & Al Kiyumi, N. (2017). The causes, impacts and mitigations of delay in megaprojects in the Sultanate of Oman. Journal of Financial Management of Property and Construction, 22(3), 286–302. https://doi.org/10.1108/JFMPC-11-2016-0052
Pai, S., Patnaik, B., Mittal, A., & Anand, N. (2018). Identification of risks causing time and cost overrun in roads and highway projects in India. Interna-tional Journal of Civil Engineering and Technology, 9(3), 683–697.
Patil, S., Gupta, A., Desa, D., & Sajane, A. (2013). Causes of delay in Indian transportation infrastructure projects. International Journal of Research in Engineering and Technology, 2(11), 71–80.
Peters, M., Godfrey, C., McInerney, P., Baldini Soares, C., Khalil, H., & Parker, D. (2017). Chapter 11: Scoping Reviews. In: Aromataris E, Munn Z (Edi-tors). Joanna Briggs Institute Reviewer’s Manual.
Rachid, Z., Toufik, B., & Mohammed, B. (2018). Causes of schedule delays in construction projects in Algeria. International Journal of Construction Management, 3599, 1–11. https://doi.org/10.1080/15623599.2018.1435234
Ramli, M. Z., Nordin, A., Roslin, N. T., Hamid, N. B., Azman, N. S., & Zahari, N. M. (2019). Causes of construction delay for housing projects in Malaysia. AIP Conference Proceedings, 2129(July), 1–5. https://doi.org/10.1063/1.5118038
Santoso, D., & Soeng, S. (2016). Analyzing delays of road construction projects in Cambodia: causes and effects. Journal of Management in Engineering, 32(6), 1–11. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000467.
Sayed, A. El, Mamoua, E., & Novali, A. (2020). The lack of techniques used in management as a factor causing delays in construction projects in B&H and other delay factors detected. Springer Nature Switzerland, 76, 728–735. https://doi.org/10.1007/978-3-030-18072-0
Shengea, N. W., Misra, R. N., & Mishra, S. K. (2020). Construction delay analysis of some Indian hydropower projects. Water and Energy International, 62r(10), 61–67.
Singh, S., Bala, A., Dixit, S., & Varshney, D. (2018). Critical analysis of causes of delay in residential construction projects in India. International Journal of Civil Engineering and Technology, 9(1), 330–345.
Sweis, G., Sweis, R., Abu, A., & Shboul, A. (2008). Delays in construction projects: The case of Jordan. International Journal of Project Management. https://doi.org/10.1016/j.ijproman.2007.09.009
Tebeje Zewdu, Z. (2016). Construction Projects Delay and Their Antidotes: The Case of Ethiopian Construction Sector. International Journal of Business and Economics Research, 5(4), 113. https://doi.org/10.11648/j.ijber.20160504.16
Walker, D. H. t., & Vines, M. W. (2000). Australian multi-unit residential project construction time performance factors. Engineering, Construction and Architectural Management. https://doi.org/10.1108/eb021152
Wang, T., Ford, D., Chong, H., & Zhang, W. (2018). Causes of delays in the construction phase of Chinese building projects. Engineering, Construction and Architectural Management, 25(11), 1534–1551. https://doi.org/10.1108/ECAM-10-2016-0227
Wang, Y., Han, Q., Vries, B., & Zuo, J. (2016). How the public reacts to social impacts in construction projects? A structural equation modeling study. International Journal of Project Management, 34(8), 1433–1448. https://doi.org/10.1016/j.ijproman.2016.07.008
Yates, J., & Eskander, A. (2002). Construction total project management planning issues. Project Management Journal, (March), 37–48.
Youniss, A., Ismail, A. Bin, Khoiry, M. A., Arhad, I., & Irtema, H. (2017). A conceptual model of delay factors affecting road construction projects in Libya. Journal of Engineering Science and Technology, 12(January 2018), 3286–3298.
Zafar, I., Wuni, I. Y., Shen, G. Q. P., & Ahmed, S. (2019). A fuzzy synthetic evaluation analysis of time overrun risk factors in highway projects of terror-ism-affected countries: the case of Pakistan. International Journal of Construction Management, 0(0), 1–19. https://doi.org/10.1080/15623599.2019.1647634
Downloads
Published
How to Cite
Issue
Section
License
Copyright (c) 2023 Guillermo Mejía, Omar Sánchez, Karen Castañeda, Eugenio Pellicer
This work is licensed under a Creative Commons Attribution-NonCommercial-NoDerivatives 4.0 International License.