Project characteristic-based performance prediction model for school constructions: hierarchical regression approach

Authors

  • Gokhan Kazar Civil Engineering Department, Istanbul Gelisim University, Istanbul (Turkey)
  • Mahmut Kucuk Civil Engineering Department, Istanbul Gelisim University, Istanbul (Turkey)

DOI:

https://doi.org/10.7764/RDLC.23.2.296

Abstract

Project underperformance remains a significant concern in the construction industry. The majority of prior studies have focused on identifying the subjective factors that affect project performance. However, there are currently no in-depth studies evaluating the influence of project characteristics and managerial/organizational obstacles on construction project performance for design-bid-build projects using empirical data. Therefore, this study aims to present a predictive model that illustrates the correlation between project characteristics, managerial/organizational complexity and difficulties, and construction project performance. Project data relating to the construction of 101 public schools within a developing country was collected. Subsequently, the project characteristics were identified, and two performance indicators (schedule performance index and cost performance index) were calculated for each project. A survey was conducted with construction professionals who took part in all of the control and management processes of these school projects to evaluate their managerial and organizational difficulties. Hierarchical regression model approach and correlation analyses were employed to develop the predictor model. The results indicate that factors such as location, school type, and project duration significantly predict both the schedule performance and managerial and organizational difficulties in school construction. An indirect correlation, rather than a direct association, was found between schedule performance and managerial and organizational difficulties. The proposed model will be a helpful guide for construction professionals, engineering managers and government decision-makers seeking to improve the performance of "design-bid-build" school construction projects. We suggest integrating the qualification-based selection (QBS) system into traditional procurement methods for public investments.

Downloads

Download data is not yet available.

References

Abou Chakra, H., and Ashi, A. (2019). Comparative analysis of design/build and design/bid/build project delivery systems in Lebanon. Journal of Industrial Engineering International, 15, 147–152. https://doi.org/10.1007/s40092-019-00323-1

Akinwande, M. O., Dikko, H. G., and Samson, A. (2015). Variance Inflation Factor: As a Condition for the Inclusion of Suppressor Variable(s) in Regression Analysis. Open Journal of Statistics, 05(07), 754–767. https://doi.org/10.4236/ojs.2015.57075

Alshihri, S., Al‐gahtani, K., and Almohsen, A. (2022). Risk Factors That Lead to Time and Cost Overruns of Building Projects in Saudi Arabia. Buildings, 12(7). https://doi.org/10.3390/buildings12070902

Amoatey, C. T., Ameyaw, Y. A., Adaku, E., and Famiyeh, S. (2015). Analysing delay causes and effects in Ghanaian state housing construction projects. International Journal of Managing Projects in Business. https://doi.org/10.1108/IJMPB-04-2014-0035

Baccarini, D. (1999). The Logical Framework Method for Defining Project Success. Project Management Journal, 30(4), 25–32. https://doi.org/10.1177/875697289903000405

Barrientos-Orellana, A., Ballesteros-Pérez, P., Mora-Melia, D., González-Cruz, M. C., and Vanhoucke, M. (2022). Stability and accuracy of deterministic project duration forecasting methods in earned value management. Engineering, Construction and Architectural Management, 29(3), 1449–1469. https://doi.org/10.1108/ECAM-12-2020-1045

Batselier, J., and Vanhoucke, M. (2015). Empirical Evaluation of Earned Value Management Forecasting Accuracy for Time and Cost. Journal of Construction Engineering and Management, 141(11). https://doi.org/10.1061/(asce)co.1943-7862.0001008

Bringula, R. P., Moraga, S. D., Catacutan, A. E., Jamis, M. N., and Mangao, D. F. (2018). Factors influencing online purchase intention of smartphones: A hierarchical regression analysis. Cogent Business and Management, 5(1), 1–18. https://doi.org/10.1080/23311975.2018.1496612

Calahorra-Jimenez, M., Alarcón, L. F., Torres-Machi, C., Chamorro, A., and Molenaar, K. (2020). Improving cost performance in design-bid-build road projects by mapping the reasons for cost overruns into the project phases. Revista de La Construccion, 19(2), 334–345. https://doi.org/10.7764/RDLC.19.2.334

Çevikbaş, M., and Işık, Z. (2021). An overarching review on delay analyses in construction projects. Buildings, 11(3). https://doi.org/10.3390/buildings11030109

Chan, A. P. C., and Chan, A. P. L. (2004). Key performance indicators for measuring construction success. In Benchmarking (Vol. 11, Issue 2, pp. 203–221). https://doi.org/10.1108/14635770410532624

Chan, A. P. C., and Chan, A. P. L. (2009). Identifying key performance indicators for use in control of pre-project stage process in construction. International Journal of Productivity and Performance Management, 11(2), 160–173. https://www-emeraldinsight-com.ezproxy.usc.edu.au/doi/pdfplus/10.1108/14635770410532624

Chan, A. P. C., Scott, D., and Chan, A. P. L. (2004). Factors Affecting the Success of a Construction Project. Journal of Construction Engineering and Management, 130(1), 153–155. https://doi.org/10.1061/(asce)0733-9364(2004)130:1(153)

Chileshe, N., and Berko, P. D. (2010). Causes of project cost overruns within the Ghanaian road construction sector. Proceedings 5th Built Environment Conference, July, 67–80.

Cho, K. M., Hong, T. H., and Hyun, C. T. (2009). Effect of project characteristics on project performance in construction projects based on structural equation model. Expert Systems with Applications, 36(7), 10461–10470. https://doi.org/10.1016/j.eswa.2009.01.032

Czemplik, A. (2014). Application of earned value method to progress control of construction projects. Procedia Engineering, 91, 424–428. https://doi.org/10.1016/j.proeng.2014.12.087

Demirkesen, S., and Ozorhon, B. (2017). Measuring project management performance: Case of construction industry. Engineering Management Journal, 29(4), 258-277, https://doi.org/10.1080/10429247.2017.1380579.

Durdyev, S. (2020). Review of construction journals on causes of project cost overruns. Engineering, Construction and Architectural Management, 28(4), 1241–1260. https://doi.org/10.1108/ECAM-02-2020-0137

Egwim, C. N., Alaka, H., Toriola-Coker, L. O., Balogun, H., Ajayi, S., and Oseghale, R. (2021). Extraction of underlying factors causing construction projects delay in Nigeria. Journal of Engineering, Design and Technology. https://doi.org/10.1108/JEDT-04-2021-0211

Franceschini, F., Galetto, M., and Turina, E. (2009). Service quality monitoring by performance indicators: A proposal for a structured methodology. International Journal of Services and Operations Management, 5(2), 251–273. https://doi.org/10.1504/IJSOM.2009.023235

Gunduz, M., and Elsherbeny, H. A. (2020). Operational Framework for Managing Construction-Contract Administration Practitioners’ Perspective through Modified Delphi Method. Journal of Construction Engineering and Management. https://doi.org/10.1061/(asce)co.1943-7862.0001768

Gunduz, M., and Tehemar, S. R. (2020). Assessment of delay factors in construction of sport facilities through multi criteria decision making. Production Planning and Control, 31(15), 1291–1302. https://doi.org/10.1080/09537287.2019.1704903

Hampson, K. D., Kraatz, J. A., and Sanchez, A. X. (2014). The global construction industry and RandD. In R and D Investment and Impact in the Global Construction Industry. https://doi.org/10.4324/9781315774916

Haponava, T., and Al-Jibouri, S. (2012). Proposed System for Measuring Project Performance Using Process-Based Key Performance Indicators. Journal of Management in Engineering, 28(2), 140–149. https://doi.org/10.1061/(asce)me.1943-5479.0000078

Hashem M. Mehany, M. S., Bashettiyavar, G., Esmaeili, B., and Gad, G. (2018). Claims and Project Performance between Traditional and Alternative Project Delivery Methods. Journal of Legal Affairs and Dispute Resolution in Engineering and Construction, 10(3). https://doi.org/10.1061/(asce)la.1943-4170.0000266

Haynes, N. S., and Love, P. E. D. (2004). Psychological adjustment and coping among construction project managers. Construction Management and Economics. https://doi.org/10.1080/0144619042000201330

Heravi, G., and Ilbeigi, M. (2012). Development of a comprehensive model for construction project success evaluation by contractors. Engineering, Construction and Architectural Management, 19(5), 526–542. https://doi.org/10.1108/09699981211259603

Johnson, R. M., and Babu, R. I. I. (2020). Time and cost overruns in the UAE construction industry: a critical analysis. International Journal of Construction Management. https://doi.org/10.1080/15623599.2018.1484864

Kaming, P. F., Olomolaiye, P. O., Holt, G. D., and Harris, F. C. (1997). Factors influencing construction time and cost overruns on high-rise projects in Indonesia. Construction Management and Economics, 15(1), 83–94. https://doi.org/10.1080/014461997373132

Kavuma, A., Ock, J., and Jang, H. (2019). Factors influencing Time and Cost Overruns on Freeform Construction Projects. KSCE Journal of Civil Engineering, 23(4), 1442–1450. https://doi.org/10.1007/s12205-019-0447-x

Kazar, G., Doğan, N. B., Ayhan, B. U., and Tokdemir, O. B. (2022). Quality Failures–Based Critical Cost Impact Factors: Logistic Regression Analysis. In Journal of Construction Engineering and Management (Vol. 148, Issue 12). https://doi.org/10.1061/(asce)co.1943-7862.0002412

Kerzner, H. (2014). Project Management Best Practices: Achieving Global Excellence. In Project Management Best Practices: Achieving Global Excellence (Vol. 9781118657). https://doi.org/10.1002/9781118835531

Kim, B.-C., and Reinschmidt, K. F. (2010). Probabilistic Forecasting of Project Duration Using Kalman Filter and the Earned Value Method. Journal of Construction Engineering and Management, 136(8), 834–843. https://doi.org/10.1061/(asce)co.1943-7862.0000192

Leon, H., Osman, H., Georgy, M., and Elsaid, M. (2018). System Dynamics Approach for Forecasting Performance of Construction Projects. Journal of Management in Engineering, 34(1). https://doi.org/10.1061/(asce)me.1943-5479.0000575

Leung, M., Liang, Q., and Chan, I. Y. S. (2017). Development of a Stressors–Stress–Performance–Outcome Model for Expatriate Construction Professionals. Journal of Construction Engineering and Management. https://doi.org/10.1061/(asce)co.1943-7862.0001266

Ma, L., and Fu, H. (2020). Exploring the influence of project complexity on the mega construction project success: a qualitative comparative analysis (QCA) method. Engineering, Construction and Architectural Management, 27(9), 2429–2449. https://doi.org/10.1108/ECAM-12-2019-0679

Marzouk, M. M., and Gaid, E. F. (2018). Assessing Egyptian construction projects performance using principal component analysis. International Journal of Productivity and Performance Management, 67(9), 1727–1744. https://doi.org/10.1108/IJPPM-06-2017-0134

McKinsey Global Institute. (2017). Reinventing Construction: A Route To Higher Productivity. In Mckinsey Global Insititute (Issue February). http://www.mckinsey.com/industries/capital-projects-and-infrastructure/our-insights/reinventing-construction-through-a-productivity-revolution

Mellado, F., Lou, E. C. W., and Becerra, C. L. C. (2020). Synthesising performance in the construction industry: An analysis of performance indicators to promote project improvement. Engineering, Construction and Architectural Management, 27(2), 579–608. https://doi.org/10.1108/ECAM-09-2018-0419

Meng, X. (2012). The effect of relationship management on project performance in construction. International Journal of Project Management, 30(2), 188–198. https://doi.org/10.1016/j.ijproman.2011.04.002

Minchin, R. E., Li, X., Issa, R. R., and Vargas, G. G. (2013). Comparison of Cost and Time Performance of Design-Build and Design-Bid-Build Delivery Systems in Florida. Journal of Construction Engineering and Management, 139(10). https://doi.org/10.1061/(asce)co.1943-7862.0000746

Molenaar, K. R., Sobin, N., and Antillón, E. I. (2010). A synthesis of best-value procurement practices for sustainable design-build projects in the public sector. Journal of Green Building, 5(4), 148–157. https://doi.org/10.3992/jgb.5.4.148

Montalbán-Domingo, L., García-Segura, T., Amalia Sanz, M., and Pellicer, E. (2019). Social Sustainability in Delivery and Procurement of Public Construction Contracts. Journal of Management in Engineering, 35(2). https://doi.org/10.1061/(asce)me.1943-5479.0000674

Moon, H., Kim, K., Lee, H.-S., Park, M., Williams, T. P., Son, B., and Chun, J.-Y. (2020). Cost Performance Comparison of Design-Build and Design-Bid-Build for Building and Civil Projects Using Mediation Analysis. Journal of Construction Engineering and Management, 146(9). https://doi.org/10.1061/(asce)co.1943-7862.0001873

Moradi, S., Ansari, R., and Taherkhani, R. (2022). A Systematic Analysis of Construction Performance Management: Key Performance Indicators from 2000 to 2020. Iranian Journal of Science and Technology - Transactions of Civil Engineering, 46(1), 15–31. https://doi.org/10.1007/s40996-021-00626-7

Mpofu, B., Ochieng, E. G., Moobela, C., and Pretorius, A. (2017). Profiling causative factors leading to construction project delays in the United Arab Emirates. Engineering, Construction and Architectural Management. https://doi.org/10.1108/ECAM-05-2015-0072

Mulla, S. S., and Waghmare, A. P. (2015). A Study of Factors Caused for Time and Cost Overruns in Construction Project and their Remedial Measures. Journal of Engineering Research and Applications Www.Ijera.Com ISSN, 5(16), 2248–962248. www.ijera.com

Nassar, N., and AbouRizk, S. (2014). Practical Application for Integrated Performance Measurement of Construction Projects. Journal of Management in Engineering, 30(6). https://doi.org/10.1061/(asce)me.1943-5479.0000287

Nguyen, P. H. D., Lines, B. C., and Tran, D. Q. (2018). Best-Value Procurement in Design-Bid-Build Construction Projects: Empirical Analysis of Selection Outcomes. Journal of Construction Engineering and Management, 144(10). https://doi.org/10.1061/(asce)co.1943-7862.0001550

Orihuela, P., Pacheco, S., and Orihuela, J. (2017). Proposal of Performance Indicators for the Design of Housing Projects. Procedia Engineering, 196, 498–505. https://doi.org/10.1016/j.proeng.2017.07.230

Perrenoud, A., Lines, B. C., Savicky, J., and Sullivan, K. T. (2017). Using Best-Value Procurement to Measure the Impact of Initial Risk-Management Capability on Qualitative Construction Performance. Journal of Management in Engineering, 33(5). https://doi.org/10.1061/(asce)me.1943-5479.0000535

PMI. (2005). Practice Standard for Earned Value Management. PM, March-April, 135. http://marketplace.pmi.org/Pages/ProductDetail.aspx?GMProduct=00101262001%5Cnhttp://procurement.citsolutions.edu.au/Clients/DOGPM/documentation/Earned_Value.pdf%5Cnhttp://scholar.google.com/scholar?hl=enandbtnG=Searchandq=intitle:Practice+Standard+for+Earned+

Proaño-Narváez, M., Flores-Vázquez, C., Vásquez Quiroz, P., and Avila-Calle, M. (2022). Earned Value Method (EVM) for Construction Projects: Current Application and Future Projections. Buildings, 12(3). https://doi.org/10.3390/buildings12030301

Radmacher, S. A., and Martin, D. J. (2001). Identifying significant predictors of student evaluations of faculty through hierarchical regression analysis. Journal of Psychology: Interdisciplinary and Applied, 135(3), 259–268. https://doi.org/10.1080/00223980109603696

Radujković, M., Vukomanović, M., and Burcar Dunović, I. (2010). Application of Key Performance Indicators in South-Eastern European construction. Journal of Civil Engineering and Management, 16(4), 521–530. https://doi.org/10.3846/jcem.2010.58

Reddy, M. V. (2019). Correlation Analysis and Regression Analysis. In Statistical Methods in Psychiatry Research and SPSS (pp. 163–176). https://doi.org/10.1201/9780429023309-12

Shrestha, P. P., and Fernane, J. D. (2017). Performance of Design-Build and Design-Bid-Build Projects for Public Universities. Journal of Construction Engineering and Management, 143(3). https://doi.org/10.1061/(asce)co.1943-7862.0001241

Skibniewski, M. J., and Ghosh, S. (2009). Determination of Key Performance Indicators with Enterprise Resource Planning Systems in Engineering Construction Firms. Journal of Construction Engineering and Management, 135(10), 965–978. https://doi.org/10.1061/(asce)0733-9364(2009)135:10(965)

Su, G., and Khallaf, R. (2022). Research on the Influence of Risk on Construction Project Performance: A Systematic Review. Sustainability (Switzerland), 14(11). https://doi.org/10.3390/su14116412

Tripathi, K. K., and Jha, K. N. (2018). An Empirical Study on Performance Measurement Factors for Construction Organizations. KSCE Journal of Civil Engineering, 22(4), 1052–1066. https://doi.org/10.1007/s12205-017-1892-z

Turkish Statistical Institute. (2022). Constuction Cost Index. https://data.tuik.gov.tr/Search/Search?text=inşaat maliyet endeksianddil=1

Vatcheva, K., and Lee, M. (2016). Multicollinearity in Regression Analyses Conducted in Epidemiologic Studies. Epidemiology: Open Access, 06(02). https://doi.org/10.4172/2161-1165.1000227

Wells, H. (2012). How effective are project management methodologies? An explorative evaluation of their benefits in practice. Project Management Journal, 43(6), 43–58. https://doi.org/10.1002/pmj.21302

Xiao, H., and Proverbs, D. (2003). Factors influencing contractor performance: An international investigation. Engineering, Construction and Architectural Management, 10(5), 322–332. https://doi.org/10.1108/09699980310502937

Yehiel, R. (2013). Root-Cause Analysis of Construction-Cost Overruns. Journal of Construction Engineering and Management.

Yu, T., Shen, G. Q., and Shi, Q. (2017). Comparing the Performance Quality of Design-Bid-Build and Design-Build Delivery Methods. Journal of Construction Engineering and Management, 143(4). https://doi.org/10.1061/(asce)co.1943-7862.0001262

Yuan, J., Zeng, A. Y., Skibniewski, M. J., and Li, Q. (2009). Selection of performance objectives and key performance indicators in public-private partnership projects to achieve value for money. Construction Management and Economics, 27(3), 253–270. https://doi.org/10.1080/01446190902748705

Zahoor, H., Khan, R. M., Nawaz, A., Ayaz, M., and Maqsoom, A. (2022). Project control and forecast assessment of building projects in Pakistan using earned value management. Engineering, Construction and Architectural Management, 29(2), 842–869. https://doi.org/10.1108/ECAM-11-2020-0989.

Downloads

Published

2024-08-30

How to Cite

Kazar, G., & Kucuk, M. (2024). Project characteristic-based performance prediction model for school constructions: hierarchical regression approach. Revista De La Construcción. Journal of Construction, 23(2), 296–316. https://doi.org/10.7764/RDLC.23.2.296